COVID-19 or the Coronavirus is having an unprecedented and, frankly, previously unimaginable global impact.  Please click here to visit Fox’s Coronavirus Resource Center for links to free webinars and articles offering practical guidance to companies of all sizes on a variety of legal issues.

Government contractors are already feeling the effects of the pandemic.  Breakdowns

COVID-19 or the Coronavirus is having an unprecedented and, frankly, previously unimaginable global impact.  Please click here to visit Fox’s Coronavirus Resource Center for links to free webinars and articles offering practical guidance to companies of all sizes on a variety of legal issues.

Government contractors are already feeling the effects of the pandemic.  Breakdowns

COVID-19 or the Coronavirus is having an unprecedented and, frankly, previously unimaginable global impact.  Please click here to visit Fox’s Coronavirus Resource Center for links to free webinars and articles offering practical guidance to companies of all sizes on a variety of legal issues.

Government contractors are already feeling the effects of the pandemic.  Breakdowns

Please join us for Fox Rothschild’s Federal Government Contracts Symposium on March 30-31, 2020 at The Mayflower Hotel in Washington, D.C.

Space is limited, so please use this link to register and view the complete itinerary.

Symposium attendees will receive targeted sessions from Fox’s Government Contracts attorneys on cutting edge issues in government contracting.

Contract Disputes Act (CDA) claims offer Government Contractors the opportunity to recover costs incurred due to Government-caused changes or delays.  While the initial focus often rests on proving liability, a recent Court of Federal Claims (COFC) decision highlights the danger of failing to prove entitlement to damages.

In other words, claims can present the danger

When a contractor delivers goods to the government that do not conform to the precise requirements of the contract, the results are usually . . . not goodWhen the agency specifies certain products in the contract, the contractor should plan to satisfy the exact specifications (or prepare to suffer the consequences).

Two weeks ago, I presented on Common Issues in Government Contract Interpretation.  The course examined common issues encountered by government contractors in bidding on and performing government contracts – as well as the dispute resolution process under the Contract Disputes Act.

One of the course’s major topics was the Plain Meaning Rule – the

Join me today, Monday July 15, 2019 at 3:00 p.m. (Eastern) for Lawline’s Live Course: KEY QUESTIONS OF CONTRACT INTERPRETATION IN GOVERNMENT CONTRACTS.

During the 90-minute course, I’ll cover the key principles of contract interpretation as they relate to government contracting.  To take best take advantage our my limited time and maximize value for

Recently on the blog, I covered one of the major risks encountered by construction contractors – subsurface or unexpected physical conditions discovered after the work begins (commonly known as  Differing Site Conditions under Federal Acquisition Regulation (FAR) 52.236-2).

In that post, I explained that a government contractor that uncovers a Differing Site Condition on a

Do contractors need to wait for a project to be complete to file a delay claim? The answer is a resounding NO! There is no reason for a contractor to finance a government-caused delay for any longer than absolutely necessary.

The Civilian Board of Contract Appeals (CBCA) recently drove this point home in CTA I